Design and supervision of the reconstruction project of Line 149 Gankeng Bridge and Ruixing Bridge

Entrusting unit : Maintenance Engineering Office of the Second District of the General Administration of Highways of the Ministry of Communications
Program Location : Zhushan Town, Nantou County
Programme Duration : 
    Republic of China planned and designed to supervise the construction, and opened to traffic in December 94
Program Overview : 
    The total length of the steel box girder bridge is 420m, and the length of each span is 60m, and the bridge deck guardrail adopts a composite hollow guardrail that can maintain the protection function and penetration, which is safe and permeable, so that users can enjoy the beautiful scenery outside the bridge.