Design and supervision of Fengshan Creek Water Pipe Bridge Pipeline Replacement Project

Client : Taiwan Water Supply Company
Planned location : Zhubei City, Hsinchu County
Programme Duration : 
    The Republic of China was designed and supervised in March 95, and the water was opened to water in February 96
Program Overview : 
    The steel arch water pipe bridge is about 181.5m long, with a length of 61.5m per span and an arch height of about 8.5m on the bridge deck. The bridge girder body is inherited in a parabolic gradient way, with a beautiful appearance, and there is no such type in the adjacent bridges, which has a unique character in the local area, forming a new landmark and having the effect of enhancing the landscape.