The second safety assessment of the Mingtan Power Plant

Client : Taipower Mingtan Power Plant
Location : Shuili Township, Nantou County
Programme Duration : 
    January 97 ~ January 98 of the Republic of China
Program Overview : 
    The Cabinet Dam is a gravity concrete arch dam, completed in August 26 of the Republic of China, located on the Cabinet Creek, a tributary of Shuili Creek, and the water source is mainly the tail water of Daguan No. 1 Plant in addition to the catchment area, which is the adjustment pool of the Jugong Branch of Mingtan Power Plant. Reservoir safety is the foundation of reservoir operation and management, according to the provisions of Article 17 of the "Measures for the Inspection and Safety Assessment of Water Conservancy Structures" formulated on December 3, 92 of the Republic of China, a certain period of normal use needs to be subject to regular assessment.