Client : Water Resources Bureau of the Southern District, Water Resources Administration, Ministry of Economic Affairs
Planned Location : Built in the upper reaches of Taoyuan Township
Programme Duration :
The detailed planning and design of the Republic of China in 96~97 is scheduled to be completed before the Republic of China 101
Program Overview :
The Xinong River barrage weir is one of the main projects of the Zengwen Reservoir cross-border water diversion project, with a planned maximum water intake of 50cms, and the water intake mode of the pipe gate in the planning stage.
Work items: the main body of the barrage, the auxiliary structure of the right bank, the flood control project, the road engineering, the gate engineering, the instrument and control engineering design, the total project cost is about 2.33 billion yuan.